The Grange

Image of building

The Grange

225 Waverley Road, Malvern East 3145

Anticipated Completion 2nd Quarter 2025
Anticipated Settlement 2nd Quarter 2025

Project Progress

100%

Demolition

45%

Structure

100%

Basement

0%

Fit out

July 2024

Dear Purchasers,

We hope you and your families are well.

We are very excited to report that the progress on site is gathering momentum and next few weeks we’ll see completion of some major milestones.

The works are in full swing to complete Level 2 concrete works and commence the works to erect the roof of the building.
We are hoping to fully complete superstructure by the end of July – mid August.
Simultaneously we’ve been busy locking in various subsequent trades and preparing for the next stage of our construction program.

We will keep you posted regarding the progress on a regular basis, but if you have any queries, please do not hesitate to contact us via email info@shustin.com.

Kind regards,

The Shustin Team