Keys Estate

Image of grass

Keys Estate

46-62 Darren Road, Keysborough 3173

Anticipated Completion Early 2025
Anticipated Settlement Early 2025

December 2024

Dear Keys Estate Homeowners,

Works are progressing well on site, and for the month of December the builder is anticipating for the following works:

Lots 1-6

  • External works (landscaping commencement)

Lots 7-14

  • Fit-off, floor coverings & external works

Lots 15-20

  • Plastering, carpentry fix and painting

Lots 21-24

  • Plastering, fix including joinery installation

Lots 25-28

  • Service rough in, external lock up and plastering

The builders have experienced some minor delays with the major authority connections (mainly Gas & Electricity) which has delayed the installation of the main internal road.

Please see below the new anticipated dates for completion:

Lots 1-10 - Mid Jan 2025

Lots 11-14 - Mid Feb 2025

Lots 15-20 - Mid March 2025

Lots 21-29 - End of March 2025.

 

We are excited about the progress made and look forward to sharing more updates as construction continues in the new year. Please see the latest photos from the construction site.
Kind regards,

PARAGON DEVELOPMENT GROUP

P: +61 3 8080 5888

E: settlements@paragondg.com.au   

W: www.paragondg.com.au

IG: Instagram

Image of floor