Dear Grandview Community,
We’re pleased to share that construction at Grandview is progressing well, with works continuing steadily on site and key milestones now underway.
Recently Completed Milestones:
- Completion of site demolition works.
- Piling has been completed.
- Completion of shotcreting.
- Installation of in-ground plumbing has now been completed.
- Completion of in-ground footings.
- Successful crane erection.
Works to follow in the next four to eight weeks:
- Basement 2 ground slab to be poured this week.
- Construction of Basement 2 structural walls.
- Pouring of the Basement 1 floor slab.
- Formation of Basement 1 structural walls.
- Commencement of the Ground floor slab.
The anticipated completion is May 2027.
The Grandview Design Team will continue to provide regular updates as construction progresses and key milestones are achieved.
In the meantime, we invite you to view the latest site imagery below, offering a glimpse of what’s taking shape behind the scenes.
Kind Regards,
The Grandview Design Team