Authenticated is false

First Light

city

First Light

28 Albert Road, South Melbourne, 3205

Anticipated Completion Q1 2027

Information

Project Progress

100%

Demolition

34%

Structure

70%

Basement

5%

Fitout

40%

Total Progress

February 2026

Dear First Light Community,

We’re pleased to share the latest progress on-site, with construction continuing to advance steadily under the management of Ironside and DCF Property.

Works completed throughout January 2026:

  • Jumpform Jump 8 and 9 (up to L8) - Complete
  • Level 3 Pour 1 and 2 - Complete
  • Level 4 Pour 1 and 2 - Complete
  • Level 5 Formwork - Complete
  • GF & L1 High Level Services - Now underway

The build is progressing well, with completion and settlement anticipated for Q1 2027.

The below photos provide a glimpse into the activity on site, showcasing the structure now emerging above ground as key service and infrastructure works advance below.

Kind regards,

The First Light Design Team

city