Fabric

Image of building

Fabric

679-683 Glen Huntly Road, Caulfield, 3162

Anticipated Completion Late 2025
Anticipated Settlement Late 2025

December 2024

Dear Fabric purchasers,

We are pleased to bring you the construction update for the Fabric development, showcasing the progress made on-site.

Here are the key activities that have been completed on site recently:

  • Ground floor fire rating over entry completed
  • Level 2 wall framing done and water rough in has a big progress
  • Level 3 framing mainly completed
  • Level 4 framing setout completed
  • Some windows arrived and subsill + subhead installed in some areas
  • Lift overrun formwork stripping started

The following works are anticipated for next week:

  • Continue with framing, plastering, and rough-in work.
  • Continuation of window installations.
  • Continue rendering work.
  • Continue noggings work.

We are excited about the progress made and look forward to sharing more updates as construction continues. Please see the below latest photos from the construction site.

Kind Regards,

The Fabric Design Team