Dear Ascend Community,

We’re pleased to share the latest construction progress at the Ascend Blackburn, with works continuing steadily on site:

  • Unit 8–14 plastering has been completed on the first and second floors.
  • Stairs are complete in all units.
  • Unit 8–14 internal wet area waterproofing has been completed.
  • Unit 8–14 tiling works will commence in approximately 2 weeks.
  • Unit 8–14 joinery will be delivered next week.
  • External waterproofing has been completed; however, an additional waterproofing layer will be applied once weather conditions improve.
  • Once the external waterproofing is complete, ground floor plastering can commence.
  • Units 1–7 are currently running approximately 2 weeks behind Units 8–14, with all trades to progressively transition across as works are completed.
  • The external façade is now 90% complete, and the scaffolding is expected to be removed over the next few weeks.

The project’s anticipated completion is scheduled for late 2026.

We’ll continue to keep you updated as key milestones are reached.
Please find the latest site photos below.

Kind regards,
The Ascend Design Team