Ascend

building

Ascend

35-37 Whitehorse Road, Blackburn, VIC

Anticipated Completion Late 2026

Information

July 2026

Dear Ascend Community,

We’re pleased to share the latest construction progress at the Ascend Blackburn, with works continuing steadily on site.

Recent Milestones:

  • U1–14 first and second floor plastering completed.
  • U8–14 joinery installation progressing.
  • U1–7 joinery installation to commence next week.
  • U8–14 tiling works progressing.
  • Stone benchtop measurements scheduled for next week.
  • In-ground services, including gas, water, electrical and NBN, completed.
  • Underground water tank excavation commenced.

Current forecast completion date is Q4 2026, subject to weather conditions.

We’ll continue to keep you updated as key milestones are reached.
Please find the latest site photos below.

Kind regards,
The Ascend Design Team